CarwilBJ’s avatarCarwilBJ’s Twitter Archive—№ 25,404

          1. Federal Court: “Dakota Access shall shut down the pipeline and empty it of oil by August 5, 2020.”
            oh my god twitter doesn’t include alt text from images in their API
        1. …in reply to @CarwilBJ
          Energy Transfer Partners may not operate Dakota Access Pipeline while the legally required Environmental Impact Statement process goes forward, Federal judge rules. bismarcktribune.com/bakken/federal-judge-orders-dakota-access-pipeline-shut-down/article_2cc387a3-f003-5557-b356-4063123a62ad.html
      1. …in reply to @CarwilBJ
        Judge James Boasberg: "Given the seriousness of the Corps' ... error, the impossibility of a simple fix, … and the potential harm each day the pipeline operates, the Court is forced to conclude that the flow of oil must cease."
    1. …in reply to @CarwilBJ
      Ruling upholds the right to PRIOR evaluation of environmental impact: NEPA requires "a detailed environmental impact statement be made for a ‘proposed’ action makes clear that agencies must take the required hard look *before* taking that action"
  1. …in reply to @CarwilBJ
    Boasberg ruling: "there is no doubt that allowing oil to flow through the pipeline during remand risks the potentially disruptive effect about which the Tribes are most concerned — a spill under Lake Oahe." bloomberglaw.com/public/desktop/document/STANDINGROCKSIOUXTRIBEvUNITEDSTATESARMYCORPSOFENGINEERSDocketNo11/7?1594051642